Please note that due to the nature of this work which can be affected by inclement weather, the activities described below may be affected by up to 2 weeks.
Week 24
- Continued construction of the superstructure brickwork to the external cavity wall at first floor level.
- Installation of the curtain walling system to the Woodsmoor Lane elevation begins.
- Continuation of first fix of building services to ground and first floor levels.
- Ground floor window installation completes.
- Internal ceiling finishes commences (ceiling margins and bulkheads) at ground floor level.
- Ground floor screed laid.
Week 25
- Continued construction of the superstructure brickwork and blockwork to the external cavity wall at first floor level.
- Installation of the curtain walling system to the Woodsmoor Lane elevation continues.
- Continuation of first fix of building services to ground and first floor levels.
- Internal ceiling finishes continues (ceiling margins and bulkheads) at ground floor level.
- Plastering internal wall surfaces commences this week at ground floor level.
- Installation of new gas service supply off Woodsmoor Lane into new building completes this week.
Week 26
- Continued construction of the superstructure brickwork and blockwork to the external cavity wall at roof pike level.
- Installation of the curtain walling system to the Woodsmoor Lane elevation completes.
- Continuation of 1st fix of building services to ground and first floor levels.
- Installation of 1st floor windows carried out this week.
- Internal ceiling finishes continues (ceiling margins and bulkheads) at ground floor level.
- Plastering internal wall surfaces continues this week at ground floor level.
Week 27
- Continued construction of the superstructure brickwork and blockwork to the external cavity wall at roof pike level.
- Continuation of 1st fix of building services to ground and first floor levels.
- Internal ceiling finishes completes (ceiling margins and bulkheads) at ground floor level.
- Plastering internal wall surfaces continues this week at ground floor level.
- Site closes Friday 23rd December for Christmas holidays.
Week 28
- Site closed for Christmas holidays.
Week 29
- Site closed for Christmas holidays. Globe may have 1 operative on site Friday 6th January in preparation for reopening site next week – to be confirmed.
Week 30
- Site opens Monday 9th January following Christmas holidays.