Schedule of work

Please note that due to the nature of this work which can be affected by inclement weather, the activities described below may be affected by up to 2 weeks.

Week 24

  • Continued construction of the superstructure brickwork to the external cavity wall at first floor level.
  • Installation of the curtain walling system to the Woodsmoor Lane elevation begins.
  • Continuation of first fix of building services to ground and first floor levels.
  • Ground floor window installation completes.
  • Internal ceiling finishes commences (ceiling margins and bulkheads) at ground floor level.
  • Ground floor screed laid.

Week 25

  • Continued construction of the superstructure brickwork and blockwork to the external cavity wall at first floor level.
  • Installation of the curtain walling system to the Woodsmoor Lane elevation continues.
  • Continuation of first fix of building services to ground and first floor levels.
  • Internal ceiling finishes continues (ceiling margins and bulkheads) at ground floor level.
  • Plastering internal wall surfaces commences this week at ground floor level.
  • Installation of new gas service supply off Woodsmoor Lane into new building completes this week.

Week 26

  • Continued construction of the superstructure brickwork and blockwork to the external cavity wall at roof pike level.
  • Installation of the curtain walling system to the Woodsmoor Lane elevation completes.
  • Continuation of 1st fix of building services to ground and first floor levels.
  • Installation of 1st floor windows carried out this week.
  • Internal ceiling finishes continues (ceiling margins and bulkheads) at ground floor level.
  • Plastering internal wall surfaces continues this week at ground floor level.

Week 27

  • Continued construction of the superstructure brickwork and blockwork to the external cavity wall at roof pike level.
  • Continuation of 1st fix of building services to ground and first floor levels.
  • Internal ceiling finishes completes (ceiling margins and bulkheads) at ground floor level.
  • Plastering internal wall surfaces continues this week at ground floor level.
  • Site closes Friday 23rd December for Christmas holidays.

Week 28

  • Site closed for Christmas holidays.

Week 29

  • Site closed for Christmas holidays. Globe may have 1 operative on site Friday 6th January in preparation for reopening site next week – to be confirmed.

Week 30

  • Site opens Monday 9th January following Christmas holidays.